Live facility fit out
Four floors executed inside an operating facility under change control and methods of procedure, without interrupting the live IT load on the floors below.

Data Centre
Mumbai, Maharashtra
The project
MEPF, building management and civil structural works for the CtrlS data centre campus in Mumbai.
Project overview
Civil and interiors: fire rated partitions, epoxy and PU flooring, two hour fire doors, C strut ceiling grid, fire stopping. Electrical: HT from the floor tapping to floor HT panels and CSS, LT from CSS to rack sockets, with the free issue CSS, DG, HT and LT panels, UPS and PDUs installed and commissioned. HVAC: air cooling and liquid cooling chilled water rings, ventilation, VRF, hot aisle containment, DX dehumidifiers. IBMS and ELV: BMS, MaxCool, EPMS, VESDA, water leak detection, fire alarm, access control, PA, CCTV. Fire and PHE: double interlock pre action sprinklers, extinguishers, floor drainage.
Four floors executed inside an operating facility under change control and methods of procedure, without interrupting the live IT load on the floors below.
On floors 8 and 9 the liquid cooling chilled water ring is sized for about 90 percent of IT load and the air cooling ring for about 40 percent, with tap offs to CDU interfaces.
A dedicated IST package: a 90 day commissioning team, witnessing L2 and L3, leading L4 and L5, 275 rack load banks of 19 kW, power quality and thermography, relay and CT testing.
Chilled water rings for PAHUs, fan walls and liquid cooling CDU interfaces. Ventilation for battery, transformer and CSS rooms. VRF for support areas, hot aisle containment, DX dehumidifiers and modular supports.
MEP totals 65%: HVAC 32%, Electrical 25%, PHE 3% and FF 5%. ELV & BMS is 20% and Civil is 15%. The split illustrates scope; it does not measure contract value, quantities or progress.
Three active projects in Navi Mumbai, supported by repeat work in Hyderabad.
Start a conversation