Fast track in a live facility
The ground and first floor package delivered in three months inside an operating data centre under the operator's methods of procedure, hot work permits and controlled shutdowns.

data Centre
Mumbai, Maharashtra
The project
HVAC works for STT Data Centre Mumbai.
Project overview
HVAC supply, installation, testing and commissioning for the ground and first floors: the chilled water low side from the building headers, precision cooling installation, air side distribution and ventilation, supports and insulation, and performance verification.
The ground and first floor package delivered in three months inside an operating data centre under the operator's methods of procedure, hot work permits and controlled shutdowns.
Temperature to ±1 °C and humidity to ±5% RH, with leak tested joints and validated containment around live IT equipment.
Testing to the operator's protocol with NABL calibrated instruments and witnessed records, to ASHRAE thermal guidelines and SMACNA duct standards.
Chilled water distribution and CRAH, PAC, AHU and FCU connections. Valves, ductwork, insulation and air terminals. Ventilation for electrical, UPS and battery rooms, with precision cooling interfaces.
MEP totals 95%: HVAC 92% and Electrical 3%. ELV & BMS is 5%. The split illustrates scope; it does not measure contract value, quantities or progress.
Zero downtime on existing infrastructure through the programme, the first of three mission critical awards in Navi Mumbai.